Projects

Mill Hill East Station

Client – Morgan Sindall

SCOPE OF WORKS

Formation & Removal of Piling Mat

Excavation & Works to a New Lift Pit/Ground Beam

Reinforcement & Concreting Works

SIKA Proof Tanking Installation

Formation of Soakaway & Associated Drainage

ACO Deck Line Installation to New Walkway

Block Paving Works

Palisade Fencing Adjustments

Formation & Installation of New Access Staircase

New Pedestrian Walkway

Excavation & Reprofiling of the Site

New Perimeter Fence Supply & Installation

Landscaping Works

Workers on the Mill Hill East Project
MA Website - Mill Hill East Project

Godstone Bridge

Client – J Murphy and Sons

SCOPE OF WORKS

Bridge Refurbishment Works

Blasting & Coatings

Steel Repairs

Steel Fabrications

Brick Repairs

Vegetation Management

Virtus LONDON10

Principal Contractor – ISG, Slough UK  |  Client – Virtus

SCOPE OF WORKS

MA provided labour resources to deliver a 7.5 MW Data Centre in Slough. LONDON10 was designed to provide high-quality customer solutions. It comprises over 3,000m2 of net technical data centre space and can handle 6.6MW of IT load.


LONDON10 can be subdivided, allowing clients to have anything from a rack in a colocation space to their own suite or data hall with dedicated power and cooling.

MA Website - Virtus Project

CMI Slough

Principal Contractor – Hauwei Slough  |  Client – China Mobile International

SCOPE OF WORKS

Located in Slough Trading Estate, the CMI UK Data Centre houses more than 1,600 racks.

In addition to the reliable design of three individual fibre cable lead-ins, the facility is served by a dual power supply from two different power substations. The power system is supported by 2N Transformers and Uninterrupted Power Supply (UPS), equipped with a 10-minute backup battery under full load. The data centre’s cooling system is supported by N+1 free-cooling chiller units and N+3 water-chilled CRACs, which are served for each data hall, where six minutes of chilled water storage is reserved for continuous cooling backup.

The facility has an N+1 diesel generator configuration with fuel storage for 24 hours under full load. MA provided cabling and fibre resources to CMI, who undertook the entire scope of electrical and telecom works.

Data centre at the CMI project

All rights reserved 2024. MA Logistics Ltd. Website Design by EYEON Digital.